Project timeline

Four clearly defined phases from confirmed order to a generating plant — roughly six weeks end to end.

From order to generation

Scroll to follow the flow — each stage lights up as the project advances.

  1. 017 Days

    Finalization of Design and Drawings

    Site survey, shadow analysis and sanctioned-load check, followed by structural and electrical drawings for your approval.

    • Site survey & shadow study
    • Structural + SLD drawings
    • Customer approval sign-off
  2. 0215 Days

    Engineering, Procurement and Supply of Material

    Modules, inverters, structures, cables and the full balance of plant are engineered, procured and delivered to site.

    • Modules & inverter dispatch
    • GI structure fabrication
    • Cables and balance of plant
  3. 0310 Days

    Solar Plant Installation

    Structure erection, module mounting, inverter, AC-DC cabling, LT panel work and monitoring system installation.

    • Structure erection
    • Module & inverter mounting
    • AC-DC cabling + LT panel
  4. 0410 Days

    Commissioning and Testing

    Testing, zero-export device setup, commissioning of the plant and power evacuation to the LT panel — then handover.

    • Zero export device setup
    • Testing & commissioning
    • Monitoring app handover
42 days total

The full roadmap

A week-by-week view of the same journey — sunlight travels the rail as your project moves from drawings to live generation.

  1. Week 1

    Design & drawings

    Survey, shadow study, approvals

  2. Week 2–3

    Procurement

    Modules, inverter, structures

  3. Week 4

    Installation

    Structure, modules, cabling

  4. Week 5

    Commissioning

    Testing, zero-export, handover

  5. Day 1 onward

    Generation

    Live monitoring on your phone

Our Scope

  • Preparation of engineering drawings and design for solar structure and power plant as per relevant IS standards
  • Supply of solar modules, inverters, structures, cables and balance of plant
  • Installation of structure, modules, inverter, AC-DC cable and LT panel
  • Installation of the monitoring and controlling system
  • Commissioning of the plant and supply of power to the LT panel
  • Zero Export Device installation

Customer Scope

  • Safe storage place for material during installation and commissioning
  • Space to evacuate the solar power
  • Design and drawing approval within 7 days